Knowledge Towns InstituteHome

Policy brief 08 · Housing delivery

From Permission to Homes

Why development time belongs at the center of housing policy—and how to test a better district process.

September 12, 2026 · Revision 1

The policy proposition

Make the route from an agreed district plan to occupied homes measurable, predictable and open to scrutiny. Test whether shared decisions at district scale allow individual buildings to proceed with less repeated uncertainty.

What the evidence establishes

D’Amico, Soltas and Wang examine housing permits across 60 U.S. cities in 2000–2025. They find large differences in development times, longer permitting associated with higher prices and lower production, and a steady permitting slowdown. These relationships do not identify the effect of a particular reform.

City comparisons use 2015–19 applications. Some earlier reviews are omitted. The multifamily archetype has 20 homes; district-scale extrapolation remains untested.

Research starting point: Leonardo D’Amico, Evan Soltas and Audrey Wang, Where Is Housing Slow to Build, And Is It Getting Slower? September 2026 working paper. The authors are not represented as partners or endorsers of these proposals.

A Knowledge District delivery compact

Our proposed compact would separate decisions that need collective agreement from checks that can be applied consistently to individual buildings. Local authorities would retain responsibility for lawful approvals, safety and public interests. The compact is a policy design to investigate, not an assertion that any jurisdiction already offers these powers.

Proposed commitmentPractical design
Agree the frameworkSet development envelopes, uses, public space, access, environmental responsibilities and infrastructure phasing through a transparent district process.
Clarify compliant developmentDefine which subsequent decisions can follow published rules and which genuinely require further discretion. Establish this within the relevant legal framework.
Coordinate reviewsAssign an accountable lead and identify reviews that can run concurrently. Publish prerequisites so one unresolved utility issue does not emerge at the end.
Make the clock visibleRecord first engagement, complete application, information requests, approval, construction and lawful occupancy separately. Report both elapsed time and pauses.
Enable incremental deliveryAllow a viable first phase without requiring every later building to be financed or designed. Disclose shared infrastructure costs and responsibilities.

Measure delivery without rewarding shortcuts

Track the distribution of time, especially difficult cases, alongside completed homes, affordability, safety, environmental performance and resident benefit. A fast approval that never becomes a building is not a successful delivery outcome. Nor is a shorter official clock that merely shifts work into an unrecorded preliminary stage.

Publish withdrawals and refusals as well as successes. Explain whether delays arise from applicants, public agencies, financing, infrastructure or several parties. Avoid treating all elapsed time as government processing time.

Research program: time to first occupied building

  1. Define the intervention. Record the actual changes to review, design rules, infrastructure and decision authority. Identify which changes are essential and their implementation costs.
  2. Establish a baseline. Reconstruct whole-project timelines for comparable sites, including stalled and abandoned proposals. Agree a consistent start event before seeing results.
  3. Compare credible alternatives. Examine district reform against conventional delivery and simpler administrative changes. Match on project size, use, market, infrastructure and ownership; use phased adoption or other credible designs where feasible.
  4. Follow beyond approval. Measure time to first occupancy and later phases, completed homes, public and private costs, rents and resident outcomes. Observe enough independent places to distinguish a district effect from one unusually capable team.
  5. Publish limits and adverse results. Pre-specify outcomes, evaluate uncertainty and commission independent scrutiny before drawing a national conclusion.

What could overturn the proposition?

District planning may front-load so much negotiation that overall time rises. Infrastructure, weak demand or finance may dominate the schedule. Certainty may raise land prices rather than reduce household costs. A consolidated process may also disadvantage small builders. These are central tests, not exceptions to remove from the sample.

Proceed to a larger program only if the whole-process benefit exceeds implementation costs without unacceptable deterioration in safety, environmental quality or access. Where a simpler reform performs as well, use it.

Help establish a study location

We welcome municipalities, universities, researchers and development teams with a live delivery question and usable evidence. This is a proposed research program; participating places, funding and evaluators have not been appointed.

Explore a research pilot ↗

Opens a structured email for your review. Nothing is submitted automatically.